Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | VSA | 20061625 | SONWARSA MAFI W/S | 364.93 | 301.43 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 30 | 30 | Yes | 0 | NA | No | 11401.00 | 9066.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Bikapur | SONWARSA MAFI | 437157 | BADGODA | 108 | 108 | 100 | Har Gar Jal | Not Certified | 
| 2 | Ayodhya | Bikapur | SONWARSA MAFI | 437163 | SONVARSHA MAFI | 90 | 90 | 100 | Har Gar Jal | Not Certified |