Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | VSA | 20061735 | PAKADPUR &TIKRI WSS | 389.72 | 211.72 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 17324.00 | 12036.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Amaniganj | Tikti | 436506 | Tikti | 217 | 217 | 100 | Har Gar Jal | Not Certified |
| 2 | Ayodhya | Amaniganj | Tikti | 436507 | Tajpur | 136 | 136 | 100 | Har Gar Jal | Not Certified |
| 3 | Ayodhya | Amaniganj | Pakad Pur | 436519 | Pakadpur | 266 | 265 | 100 | Work In Progress | Not Certified |
| 4 | Ayodhya | Amaniganj | Pakad Pur | 436520 | Pure Sidhari | 155 | 155 | 100 | Har Gar Jal | Not Certified |