Scheme Details
DISTRICT
Ayodhya
AGENCY
VSA
SCHEME ID
20061822
SCHEME NAME
ACCHORA WSS
ESTIMATED COST
480.69
EXPENDITURE
266.76
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
25
Procured
25
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
36275.00
Meter
Length Laid
34642.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | HARRINGTONGANJ | ACCHORA | 436690 | ACCHORA | 719 | 719 | 100% | Har Ghar Jal | Not Certified |