Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | VSA | 20061833 | DOSTGRAMPUR ODI RATNATHPUR & SIRSA NIYAJPUR | 484.95 | 221.01 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 30 | 30 | Yes | 0 | NA | No | 28568.00 | 18210.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Tarun | Dostgram Pur | 437365 | Dostgram Pur | 238 | 238 | 100 | Har Gar Jal | Not Certified |
| 2 | Ayodhya | Tarun | Odi Ratnath Pur | 437369 | Odi Ratnath Pur | 242 | 242 | 100 | Har Gar Jal | Not Certified |
| 3 | Ayodhya | Tarun | Sirsa Niyajpur | 437370 | Niyajpur | 213 | 213 | 100 | Har Gar Jal | Not Certified |
| 4 | Ayodhya | Tarun | Sirsa Niyajpur | 437371 | Sirsa | 69 | 69 | 100 | Har Gar Jal | Not Certified |