Scheme Details
DISTRICT
Ayodhya
AGENCY
VSA
SCHEME ID
20061992
SCHEME NAME
AMAUNI, BHOYA & KUMHIYA WSS
ESTIMATED COST
702.27
EXPENDITURE
454.94
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
44
Procured
44
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
35106.00
Meter
Length Laid
37700.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Maya Bazar | Kumhiya | 437112 | Chachikpur | 150 | 150 | 100% | Har Ghar Jal | Not Certified |
| 2 | Ayodhya | Maya Bazar | Amauni | 437146 | Amouni | 174 | 174 | 100% | Har Ghar Jal | Not Certified |
| 3 | Ayodhya | Maya Bazar | Bhoya | 437147 | Bhoya | 206 | 206 | 100% | Har Ghar Jal | Certified |
| 4 | Ayodhya | Maya Bazar | Kumhiya | 437148 | Kumhiya | 444 | 444 | 100% | Har Ghar Jal | Not Certified |