Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Ayodhya
AGENCY VSA
SCHEME ID 20062009
SCHEME NAME PARA KAIL & SARIAYA WSS
ESTIMATED COST 372.93
EXPENDITURE 153.89
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 21040.00 Meter
Length Laid 17845.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Ayodhya Masodha Saraiya 436876 Saraya 271 271 100% Har Ghar Jal Not Certified
2 Ayodhya Masodha Para Kail 436877 Para Kail 252 252 100% Har Ghar Jal Not Certified