Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | NCC Ltd. | 20062490 | KISHUNPUR JAMUNI JJM SCHEME | 282.04 | 150.45 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 18 | 18 | Yes | 0 | NA | No | 14855.00 | 11748.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | Pasgawan | Kishunpur Jamuni | 408882 | Kishunpur Jamuni | 154 | 153 | 99 | Work In Progress | Not Certified | 
| 2 | Lakhimpur Kheri | Pasgawan | Kishunpur Jamuni | 408883 | Pipraula Mardan | 128 | 128 | 100 | Har Gar Jal | Not Certified | 
| 3 | Lakhimpur Kheri | Pasgawan | Kishunpur Jamuni | 408884 | Hariharpur | 104 | 104 | 100 | Har Gar Jal | Not Certified |