Scheme Details
DISTRICT
Moradabad
AGENCY
LC INFRA
SCHEME ID
20062534
SCHEME NAME
Birpur fatehullapur
ESTIMATED COST
279.51
EXPENDITURE
229.42
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9041.00
Meter
Length Laid
8900.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Bhagatpur Tanda | Birpur Fatehullapur | 388094 | Birpur Fatehullapur | 389 | 389 | 100% | Har Ghar Jal | Certified |
| 2 | Moradabad | Bhagatpur Tanda | Birpur Fatehullapur | 388096 | Bahdurpur Patti | 81 | 81 | 100% | Har Ghar Jal | Certified |