Scheme Details
DISTRICT
Barabanki
AGENCY
PNC-SPML-JV
SCHEME ID
20062657
SCHEME NAME
Jagsenda Water Supply Scheme
ESTIMATED COST
262.52
EXPENDITURE
115.22
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
20
Procured
0
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9498.00
Meter
Length Laid
9080.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Fatehpur | Jagsenda | 434606 | Jagsenda | 436 | 432 | 99% | Work In Progress | Not Certified |
| 2 | Barabanki | Fatehpur | Jagsenda | 434607 | Pandri | 24 | 24 | 100% | Har Ghar Jal | Not Certified |