Scheme Details
DISTRICT
Barabanki
AGENCY
PNC-SPML-JV
SCHEME ID
20062728
SCHEME NAME
Deokalia Water Supply Scheme
ESTIMATED COST
354.95
EXPENDITURE
224.36
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13681.00
Meter
Length Laid
12630.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Masauli | DEOKALIA | 435401 | DEOKALIA | 317 | 317 | 100% | Har Ghar Jal | Certified |
| 2 | Barabanki | Masauli | DEOKALIA | 435402 | Tera | 231 | 231 | 100% | Har Ghar Jal | Certified |
| 3 | Barabanki | Masauli | DEOKALIA | 435403 | Munja Pur | 210 | 210 | 100% | Har Ghar Jal | Certified |