Scheme Details
DISTRICT
Barabanki
AGENCY
PNC-SPML-JV
SCHEME ID
20062776
SCHEME NAME
Mohammadipur & Gursel Water Supply Scheme
ESTIMATED COST
262.73
EXPENDITURE
202.14
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
63
Procured
0
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14108.00
Meter
Length Laid
14108.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Fatehpur | Gursel | 434561 | Gursel | 277 | 272 | 98% | Work In Progress | Not Certified |
| 2 | Barabanki | Fatehpur | Mohmmadipur | 434562 | Mohmmadipur | 130 | 124 | 95% | Work In Progress | Not Certified |
| 3 | Barabanki | Fatehpur | Mohmmadipur | 434563 | Dhadhauri | 86 | 80 | 93% | Work In Progress | Not Certified |
| 4 | Barabanki | Fatehpur | Mohmmadipur | 434564 | Dhadhara | 99 | 93 | 94% | Work In Progress | Not Certified |
| 5 | Barabanki | Fatehpur | Mohmmadipur | 434565 | Masudpur | 71 | 65 | 92% | Work In Progress | Not Certified |