Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20062778 | ASNAHRI GP wss | 152.96 | 107.89 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 13 | 13 | Yes | 0 | NA | No | 7884.00 | 7884.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Ramnagar | Asnahri | 448769 | Shanichara | 75 | 75 | 100 | Har Gar Jal | Not Certified |
| 2 | Basti | Ramnagar | Asnahri | 448771 | Basti Nathu | 36 | 36 | 100 | Har Gar Jal | Not Certified |
| 3 | Basti | Ramnagar | Asnahri | 448772 | Asnahari | 84 | 84 | 100 | Har Gar Jal | Not Certified |