Scheme Details
DISTRICT
Sitapur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20062879
SCHEME NAME
MULTI GP KARSSEORA - BAKAR NAGAR
ESTIMATED COST
414.48
EXPENDITURE
240.23
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
15753.00
Meter
Length Laid
15753.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Laharpur | Karsseora | 410678 | Karseora | 636 | 608 | 96% | Work In Progress | Not Certified |
| 2 | Sitapur | Laharpur | Bakar Nagar | 410721 | Bakar Nagar | 149 | 124 | 83% | Work In Progress | Not Certified |
| 3 | Sitapur | Laharpur | Bakar Nagar | 410722 | Sharifpur Kasmanda | 120 | 77 | 64% | Work In Progress | Not Certified |