Scheme Details
DISTRICT
Fatehpur
AGENCY
Power Mech Projects Ltd
SCHEME ID
20062929
SCHEME NAME
ABDULLAPUR GHURI
ESTIMATED COST
233.36
EXPENDITURE
112.69
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
18
Procured
18
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7463.00
Meter
Length Laid
7482.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Bhitaura | Abdullapur Ghuri | 427815 | Abdullapur Ghuri | 144 | 144 | 100% | Har Ghar Jal | Not Certified |
| 2 | Fatehpur | Bhitaura | Abdullapur Ghuri | 427816 | Khalilpur | 64 | 23 | 36% | Work In Progress | Not Certified |
| 3 | Fatehpur | Bhitaura | Abdullapur Ghuri | 427817 | Kamlapur | 100 | 50 | 50% | Work In Progress | Not Certified |
| 4 | Fatehpur | Bhitaura | Abdullapur Ghuri | 427818 | Sultanpur Khalsa | 85 | 28 | 33% | Work In Progress | Not Certified |