Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20062942 | MALHWAR GP wss | 242.34 | 43.55 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 9470.00 | 9000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Rudhauli | Malhwar | 450559 | Madarehna | 91 | 72 | 79 | Work In Progress | Not Certified |
| 2 | Basti | Rudhauli | Malhwar | 450560 | Malhwar | 130 | 128 | 98 | Work In Progress | Not Certified |
| 3 | Basti | Rudhauli | Malhwar | 450561 | Teloura | 94 | 85 | 90 | Work In Progress | Not Certified |
| 4 | Basti | Rudhauli | Malhwar | 450562 | Sirsia | 11 | 1 | 9 | Work In Progress | Not Certified |