Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Aligarh
AGENCY ION EXCHANGE
SCHEME ID 20062999
SCHEME NAME UTTAMPUR WATER SUPPLY SCHEME
ESTIMATED COST 364.29
EXPENDITURE 146.34
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 27
Procured 27 KW
Work Status No
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 19771.00 Meter
Length Laid 18882.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Aligarh Gonda Uttampur 395215 Uttampur 529 529 100% Har Ghar Jal Not Certified
2 Aligarh Gonda Uttampur 395216 Vrish Bhanpur 111 111 100% Har Ghar Jal Not Certified