Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Aligarh | ION EXCHANGE | 20063015 | MALAV WATER SUPPLY SCHEME | 722.79 | 116.00 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | NA | 15 | NA | No | 13943.80 | 13943.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Aligarh | Tappal | Malav | 394288 | Malav | 1143 | 1075 | 94 | Work In Progress | Not Certified |
| 2 | Aligarh | Tappal | Malav | 394289 | Girdharpur | 2 | 1 | 50 | Work In Progress | Not Certified |
| 3 | Aligarh | Tappal | Malav | 394290 | Sherpur | 15 | 1 | 7 | Work In Progress | Not Certified |