Scheme Details
DISTRICT
Moradabad
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20063244
SCHEME NAME
Khaiya Khaddar Multi Village Water Supply Scheme
ESTIMATED COST
329.67
EXPENDITURE
167.59
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9768.00
Meter
Length Laid
9568.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Moradabad | AKKA BHIKANPUR MUSTAHKAM | 388235 | Akka Bhikanpur Mustahkam | 378 | 376 | 99% | Work In Progress | Not Certified |
| 2 | Moradabad | Moradabad | Khaiya Khadder | 388242 | Khaiya Khadder | 349 | 348 | 100% | Work In Progress | Not Certified |