Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Larsen & Toubro Ltd | 20063247 | MULTI GP BAJHA-TAHPUR Water Supply Scheme | 358.55 | 145.55 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 25 | 25 | Yes | 0 | NA | No | 23737.00 | 23737.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Reusa | Bajaha | 410862 | Bajha | 380 | 365 | 96 | Work In Progress | Not Certified |
| 2 | Sitapur | Reusa | Tahpur | 410977 | Pakauri | 152 | 116 | 76 | Work In Progress | Not Certified |
| 3 | Sitapur | Reusa | Tahpur | 410978 | Tahpur | 144 | 125 | 87 | Work In Progress | Not Certified |