Scheme Details
DISTRICT
Pratapgarh
AGENCY
Power Mech Projects Ltd
SCHEME ID
20063817
SCHEME NAME
GOKHARI & UDHRANPUR WATER SUPPLY SCHEME
ESTIMATED COST
475.31
EXPENDITURE
257.35
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
32
Procured
32
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
29114.00
Meter
Length Laid
29114.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | Lalganj Ajhara | Gokhari | 428827 | Gokhari | 457 | 450 | 98% | Work In Progress | Not Certified |
| 2 | Pratapgarh | Lalganj Ajhara | Udharanpur | 428830 | Udharanpur | 182 | 172 | 95% | Work In Progress | Not Certified |