Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Gayatri Projects LTD | 20063876 | Hardaspur Sarafan | 239.58 | 56.86 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 31 | 31 | Yes | 0 | NA | No | 7708.00 | 7519.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Vijaipur | Hardaspur Sarafan | 428553 | Hardaspur Sarafan | 220 | 220 | 100 | Har Gar Jal | Not Certified | 
| 2 | Fatehpur | Vijaipur | Hardaspur Sarafan | 428554 | Shashpur | 130 | 127 | 98 | Work In Progress | Not Certified | 
| 3 | Fatehpur | Vijaipur | Hardaspur Sarafan | 428555 | Tajnipur | 51 | 50 | 98 | Work In Progress | Not Certified |