Scheme Details
DISTRICT Deoria
AGENCY Rithwik-Koya (JV)
SCHEME ID 20063936
SCHEME NAME AGHAV, GADA URF KANUNGO, GOURA MERGED WATER SUPPLY SCHEME
ESTIMATED COST 456.53
EXPENDITURE 326.97
AUTOMATION STATUS
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 31
Procured 31 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 21540.13 Meter
Length Laid 22450.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Deoria Bankata Gada Urf Kanungo 460863 Gada Urf Kanungo 163 162 99% Work In Progress Not Certified
2 Deoria Bankata Aghav 460866 Aghaw 186 186 100% Har Ghar Jal Not Certified
3 Deoria Bankata Goura 460873 Goura 125 125 100% Har Ghar Jal Not Certified
4 Deoria Bankata Goura 460874 Bankata Sirsare 89 88 99% Work In Progress Not Certified