Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | GA INFRA - BABA (JV) | 20064031 | Tilgori & Shahpur Perwa water supply scheme | 418.70 | 186.64 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | NA | 10 | NA | No | 15837.00 | 15837.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | Newada | Tilgori | 431571 | Tilgori | 423 | 395 | 93 | Work In Progress | Not Certified |
| 2 | Kaushambi | Newada | Tilgori | 431572 | Alampur | 233 | 196 | 84 | Work In Progress | Not Certified |
| 3 | Kaushambi | Newada | Shahpur Perwa | 431575 | Shahpur Perwa | 267 | 169 | 63 | Work In Progress | Not Certified |