Scheme Details
DISTRICT
Deoria
AGENCY
Rithwik-Koya (JV)
SCHEME ID
20064048
SCHEME NAME
HATA, LACHHUMAN CHAK, PARSOUNI RAGHUNATH MERGE GP WATER SUPPLY SCHEME
ESTIMATED COST
573.23
EXPENDITURE
293.24
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
8
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
37
Procured
45
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
24109.00
Meter
Length Laid
26700.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
9 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Bankata | Lachhuman Chak | 460945 | Lachhuman Chak | 91 | 91 | 100% | Har Ghar Jal | Not Certified |
| 2 | Deoria | Bankata | Lachhuman Chak | 460946 | Bhatwalia Gosai | 52 | 52 | 100% | Har Ghar Jal | Not Certified |
| 3 | Deoria | Bankata | Lachhuman Chak | 460947 | Badha Chhapar | 88 | 88 | 100% | Har Ghar Jal | Not Certified |
| 4 | Deoria | Bankata | Parsouni Raghunath | 460949 | Parsouni Raghunath | 83 | 74 | 89% | Work In Progress | Not Certified |
| 5 | Deoria | Bankata | Parsouni Raghunath | 460950 | Chourangi Chak | 89 | 83 | 93% | Work In Progress | Not Certified |
| 6 | Deoria | Bankata | Parsouni Raghunath | 460951 | Basti Chhapar | 50 | 42 | 84% | Work In Progress | Not Certified |
| 7 | Deoria | Bankata | Hata | 460975 | Hata | 221 | 220 | 100% | Work In Progress | Not Certified |
| 8 | Deoria | Bankata | Hata | 460976 | Sri Rampur | 103 | 100 | 97% | Work In Progress | Not Certified |
| 9 | Deoria | Bankata | Lachhuman Chak | 680812 | Bhatwali Jamin | 112 | 107 | 96% | Work In Progress | Not Certified |