Scheme Details
DISTRICT Mau
AGENCY LC INFRA
SCHEME ID 20064254
SCHEME NAME Baharipur Gram Panchayat Water Supply Scheme
ESTIMATED COST 169.15
EXPENDITURE 62.99
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 11
Procured 11 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 3713.00 Meter
Length Laid 3200.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Mau Pardaha Baharipur 465709 Baharipur 340 269 79% Work In Progress Not Certified