Scheme Details
DISTRICT
Mau
AGENCY
LC INFRA
SCHEME ID
20064268
SCHEME NAME
Haldharpur Gram Panchayat Water Supply Scheme
ESTIMATED COST
191.51
EXPENDITURE
112.34
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
21
Procured
21
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
19534.00
Meter
Length Laid
18260.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Ratanpura | Haldharpur | 465857 | Haldharpur | 519 | 519 | 100% | Har Ghar Jal | Not Certified |
| 2 | Mau | Ratanpura | Haldharpur | 465858 | Bhairo Sofipur | 100 | 100 | 100% | Har Ghar Jal | Not Certified |