Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Mau | LC INFRA | 20064433 | Madauli Budhanpur Gram Panchayat Water Supply Scheme | 281.25 | 149.35 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 18 | 175 | Yes | 0 | NA | No | 17503.00 | 14310.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Ratanpura | MADAILI BADHANPURA | 465783 | Madauli Budhanpur | 471 | 450 | 96 | Work In Progress | Not Certified |
| 2 | Mau | Ratanpura | MADAILI BADHANPURA | 465784 | Basarikhpur | 139 | 139 | 100 | Har Gar Jal | Not Certified |
| 3 | Mau | Ratanpura | MADAILI BADHANPURA | 655541 | PAKADIKOL | 7 | 7 | 100 | Har Gar Jal | Not Certified |