Scheme Details
DISTRICT
Mau
AGENCY
LC INFRA
SCHEME ID
20064433
SCHEME NAME
Madauli Budhanpur Gram Panchayat Water Supply Scheme
ESTIMATED COST
281.25
EXPENDITURE
157.05
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
18
Procured
175
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17503.00
Meter
Length Laid
14310.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Ratanpura | MADAILI BADHANPURA | 465783 | Madauli Budhanpur | 471 | 450 | 96% | Work In Progress | Not Certified |
| 2 | Mau | Ratanpura | MADAILI BADHANPURA | 465784 | Basarikhpur | 139 | 139 | 100% | Har Ghar Jal | Not Certified |
| 3 | Mau | Ratanpura | MADAILI BADHANPURA | 655541 | PAKADIKOL | 7 | 7 | 100% | Har Ghar Jal | Not Certified |