Scheme Details
DISTRICT Lucknow
AGENCY NCC Ltd.
SCHEME ID 20064540
SCHEME NAME Kamalpur Lodhaura & Tikari Kala
ESTIMATED COST 365.03
EXPENDITURE 244.40
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 25
Procured 25 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 19577.00 Meter
Length Laid 19577.00 Meter

Scheme Assigned Villages

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Lucknow Mal Kamalpur Lodhaura 415376 Kamalpur Lodhaura 220 220 100% Har Ghar Jal Certified
2 Lucknow Mal Kamalpur Lodhaura 415377 Didhara 173 173 100% Har Ghar Jal Certified
3 Lucknow Mal Tikari Kala 415411 Tikari Kala 204 184 90% Work In Progress Not Certified