DISTRICT Sitapur
AGENCY NCC Ltd.
SCHEME ID 20064702
SCHEME NAME Umari Salempur & Sikanderpur Water Supply Scheme
ESTIMATED COST 354.85
EXPENDITURE 168.70
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 25
Procured 25 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 14660.00 Meter
Length Laid 14124.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sitapur Hargaon Umri Salempur 410426 Hariboepur 177 177 100% Har Ghar Jal Not Certified
2 Sitapur Hargaon Sikanderpur 410427 Sikanderpur 241 241 100% Har Ghar Jal Not Certified
3 Sitapur Hargaon Umri Salempur 410428 Umari Salempur 248 248 100% Har Ghar Jal Not Certified