Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Hathras | BGCCPL-Ramky (JV) | 20064935 | NAGLA DAYA WSS | 256.84 | 55.57 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 10145.00 | 10130.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hathras | Mursan | Nagla Daya | 395719 | Nagla Daya | 196 | 108 | 55 | Work In Progress | Not Certified |
| 2 | Hathras | Mursan | Nagla Banarsi Prahlad | 395723 | Nagla Banarsi Prahlad | 179 | 160 | 89 | Work In Progress | Not Certified |