Scheme Details
DISTRICT
Jaunpur
AGENCY
Welspun Kaveri Infraprojects JV
SCHEME ID
20065229
SCHEME NAME
Rasra
ESTIMATED COST
579.67
EXPENDITURE
227.15
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
10
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
44
Procured
44
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
33512.00
Meter
Length Laid
33512.00
Meter
Scheme Assigned Villages
10 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Dobhi | Bagerwan | 471393 | Bagerwan | 184 | 176 | 96% | Work In Progress | Not Certified |
| 2 | Jaunpur | Dobhi | Rasra | 471407 | Jamunibari | 112 | 110 | 98% | Work In Progress | Not Certified |
| 3 | Jaunpur | Dobhi | Rasra | 471408 | Rasra | 167 | 162 | 97% | Work In Progress | Not Certified |
| 4 | Jaunpur | Dobhi | Rasra | 471409 | Sonbarsa | 28 | 25 | 89% | Work In Progress | Not Certified |
| 5 | Jaunpur | Dobhi | Rasra | 471410 | Bishunpurwa | 131 | 131 | 100% | Har Ghar Jal | Not Certified |
| 6 | Jaunpur | Dobhi | Barauti | 471411 | Chaubepur | 157 | 154 | 98% | Work In Progress | Not Certified |
| 7 | Jaunpur | Dobhi | Barauti | 471412 | Chawarwar | 50 | 47 | 94% | Work In Progress | Not Certified |
| 8 | Jaunpur | Dobhi | Barauti | 471413 | Barauti | 136 | 136 | 100% | Har Ghar Jal | Not Certified |
| 9 | Jaunpur | Dobhi | Barauti | 471414 | Chakmadhoram | 29 | 29 | 100% | Har Ghar Jal | Not Certified |
| 10 | Jaunpur | Dobhi | Barauti | 471415 | Khaliyabankat | 16 | 15 | 94% | Work In Progress | Not Certified |