Scheme Details
DISTRICT
Moradabad
AGENCY
LC INFRA
SCHEME ID
20065244
SCHEME NAME
Mathana Village Water Supply Scheme
ESTIMATED COST
453.68
EXPENDITURE
113.03
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
14
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
5579.00
Meter
Length Laid
5296.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Chhajlet | Mathana | 388005 | Mathana | 371 | 357 | 96% | Work In Progress | Not Certified |