Scheme Details
DISTRICT
Fatehpur
AGENCY
GA INFRA - BABA (JV)
SCHEME ID
20065325
SCHEME NAME
ASALPUR & SUKETI
ESTIMATED COST
398.63
EXPENDITURE
193.11
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
15
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18693.00
Meter
Length Laid
22708.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Bahua | Asalpur | 428046 | Asalpur | 308 | 308 | 100% | Har Ghar Jal | Not Certified |
| 2 | Fatehpur | Bahua | Suketi | 428116 | Suketi | 741 | 741 | 100% | Har Ghar Jal | Not Certified |
| 3 | Fatehpur | Bahua | Suketi | 428117 | Chak Wajid | 36 | 36 | 100% | Har Ghar Jal | Not Certified |
| 4 | Fatehpur | Bahua | Suketi | 428118 | Indro | 198 | 198 | 100% | Har Ghar Jal | Not Certified |