Scheme Details
DISTRICT
Hathras
AGENCY
BGCCPL-Ramky (JV)
SCHEME ID
20065328
SCHEME NAME
MUBARIKPUR KAPSIA WSS
ESTIMATED COST
449.53
EXPENDITURE
187.40
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
30
Procured
30
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13153.00
Meter
Length Laid
13000.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hathras | Sikandrarao | Mubarikpur Kapsia | 395936 | Mubarikpur Kapsia | 828 | 818 | 99% | Work In Progress | Not Certified |