Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Budaun
AGENCY PNC-SPML-JV
SCHEME ID 20065352
SCHEME NAME lalpur khadar water supply scheme
ESTIMATED COST 200.88
EXPENDITURE 64.49
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 13
Procured 13 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 6390.00 Meter
Length Laid 6390.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Budaun Dataganj Lalpur Khadar 402370 Lalpur Khadar 145 143 99% Work In Progress Not Certified
2 Budaun Dataganj Lalpur Khadar 402371 Pooran Bheda 79 77 97% Work In Progress Not Certified
3 Budaun Dataganj Lalpur Khadar 402372 Payyi Biza Kham 70 68 97% Work In Progress Not Certified