Scheme Details
DISTRICT
Aligarh
AGENCY
PNC-SPML-JV
SCHEME ID
20065365
SCHEME NAME
LAHRA SALEMPUR WSS
ESTIMATED COST
340.10
EXPENDITURE
176.82
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13534.00
Meter
Length Laid
12000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Aligarh | Bijauli | Lahra Salempur | 394866 | Lahra Salempur | 812 | 812 | 100% | Har Ghar Jal | Not Certified |
| 2 | Aligarh | Bijauli | Lahra Salempur | 394867 | Govala | 124 | 124 | 100% | Har Ghar Jal | Not Certified |