Scheme Details
DISTRICT
Jaunpur
AGENCY
Welspun Kaveri Infraprojects JV
SCHEME ID
20065569
SCHEME NAME
PADUMPUR KHAS
ESTIMATED COST
229.23
EXPENDITURE
65.95
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
20
Procured
0
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10777.00
Meter
Length Laid
10777.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Karanjakala | Padumpur Khas | 470281 | Padumpur Khas | 138 | 137 | 99% | Work In Progress | Not Certified |
| 2 | Jaunpur | Karanjakala | Padumpur Khas | 470282 | Araji Padumpur I | 5 | 4 | 80% | Work In Progress | Not Certified |
| 3 | Jaunpur | Karanjakala | Padumpur Khas | 470283 | Araji Padumpur Ii | 4 | 3 | 75% | Work In Progress | Not Certified |
| 4 | Jaunpur | Karanjakala | Padumpur Khas | 470284 | Arazi Mainipur | 15 | 14 | 93% | Work In Progress | Not Certified |
| 5 | Jaunpur | Karanjakala | Padumpur Khas | 470286 | Deo Chandpur | 35 | 34 | 97% | Work In Progress | Not Certified |
| 6 | Jaunpur | Karanjakala | Padumpur Khas | 470287 | Chak Hata | 18 | 17 | 94% | Work In Progress | Not Certified |