Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Larsen & Toubro Ltd | 20065901 | Buapur_Bhane Mau_Chaq Nooruddin Water Supply Scheme | 362.24 | 151.36 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 35 | 35 | Yes | 0 | NA | No | 25019.00 | 25019.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Bahariya | Chak Nuruddin Urf Nikdilpur | 432147 | Chaq Nooruddin Urf Nagdilpur | 160 | 160 | 100 | Har Gar Jal | Not Certified |
| 2 | Prayagraj | Bahariya | Buapur | 432177 | Buapur | 350 | 350 | 100 | Har Gar Jal | Not Certified |
| 3 | Prayagraj | Bahariya | Bhane Mau | 432186 | Bhane Mau | 220 | 220 | 100 | Har Gar Jal | Not Certified |