Scheme Details
DISTRICT Sitapur
AGENCY NCC Ltd.
SCHEME ID 20065913
SCHEME NAME Kharwaliya
ESTIMATED COST 258.29
EXPENDITURE 213.55
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 18
Procured 18 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 10726.00 Meter
Length Laid 10726.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sitapur Sidhauli Kharwaliya 411773 Kharwaliya 366 366 100% Har Ghar Jal Certified