Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | NCC Ltd. | 20065918 | Ladilapur | 330.31 | 215.74 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 21 | 21 | Yes | 0 | NA | No | 19145.00 | 18200.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Reusa | Ladilapur | 410938 | Ladilapur | 287 | 285 | 99 | Work In Progress | Not Certified |
| 2 | Sitapur | Reusa | Ladilapur | 410939 | Bhainsi | 50 | 49 | 98 | Work In Progress | Not Certified |
| 3 | Sitapur | Reusa | Ladilapur | 410940 | Sikari Mafi | 97 | 91 | 94 | Work In Progress | Not Certified |