Scheme Details
DISTRICT
Budaun
AGENCY
PNC-SPML-JV
SCHEME ID
20065936
SCHEME NAME
Pinsaul & Karanpur water supply scheme
ESTIMATED COST
442.00
EXPENDITURE
195.72
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16604.00
Meter
Length Laid
16604.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Ambiapur | Pindaul | 401677 | Pindaul | 542 | 542 | 100% | Har Ghar Jal | Certified |
| 2 | Budaun | Ambiapur | Pindaul | 401678 | Hardaspur | 48 | 48 | 100% | Har Ghar Jal | Certified |
| 3 | Budaun | Ambiapur | Karanpur | 401679 | Karanpur | 215 | 215 | 100% | Har Ghar Jal | Not Certified |