Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Budaun
AGENCY PNC-SPML-JV
SCHEME ID 20066063
SCHEME NAME ASDHARMAI & SEHA BOURA WATER SUPPLY SCHEME
ESTIMATED COST 397.32
EXPENDITURE 161.53
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 37
Procured 37 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 16884.00 Meter
Length Laid 16884.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Budaun Mion Asdharmai 402411 Asdharmai 391 390 100% Work In Progress Not Certified
2 Budaun Mion Seha Boura 402420 Seha 215 213 99% Work In Progress Not Certified
3 Budaun Mion Seha Boura 402421 Baura 95 93 98% Work In Progress Not Certified
4 Budaun Mion Seha Boura 402422 Raipura Taluka Allapur 47 45 96% Work In Progress Not Certified