Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20066122 | CHAMRAHA & CHAK IN HAIDER HUSAIN VILLAGE WATER SUPPLY SCHEME | 340.12 | 204.86 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 20 | 20 | No | 0 | NA | No | 20409.00 | 9344.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Barsathi | Bairethi | 469981 | Chak English Mohammad Hanif | 90 | 37 | 41 | Work In Progress | Not Certified | 
| 2 | Jaunpur | Barsathi | Bairethi | 469982 | Bairethi | 8 | 5 | 62 | Work In Progress | Not Certified | 
| 3 | Jaunpur | Barsathi | Bairethi | 469983 | Chak English Haidar Husain | 112 | 79 | 71 | Work In Progress | Not Certified | 
| 4 | Jaunpur | Barsathi | Chamraha | 469985 | Chamraha | 166 | 91 | 55 | Work In Progress | Not Certified |