Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Welspun Kaveri Infraprojects JV | 20066250 | Kamalpur | 253.41 | 114.10 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 30 | 0 | NA | 0 | NA | No | 23133.00 | 13762.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Badlapur | Kamalpura | 468807 | Kuchauha | 89 | 54 | 61 | Work In Progress | Not Certified |
| 2 | Jaunpur | Badlapur | Kamalpura | 468808 | Jagatpur | 63 | 42 | 67 | Work In Progress | Not Certified |
| 3 | Jaunpur | Badlapur | Kamalpura | 468809 | Chak Semaraha | 11 | 2 | 18 | Work In Progress | Not Certified |
| 4 | Jaunpur | Badlapur | Kamalpura | 468810 | Kamalpur | 181 | 173 | 96 | Work In Progress | Not Certified |
| 5 | Jaunpur | Badlapur | Sarai Gunja | 468811 | Sarai Gunja | 242 | 118 | 49 | Work In Progress | Not Certified |