Scheme Details
DISTRICT
Jaunpur
AGENCY
AFCONS
SCHEME ID
20066262
SCHEME NAME
BASHEERPUR & BAHERI GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST
331.78
EXPENDITURE
178.25
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
20663.00
Meter
Length Laid
18587.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Ramnagar | Basheerpur | 470838 | Gulalpur | 58 | 24 | 41% | Work In Progress | Not Certified |
| 2 | Jaunpur | Ramnagar | Basheerpur | 470839 | Ahadipur | 58 | 46 | 79% | Work In Progress | Not Certified |
| 3 | Jaunpur | Ramnagar | Basheerpur | 470840 | Basheerpur | 137 | 109 | 80% | Work In Progress | Not Certified |
| 4 | Jaunpur | Ramnagar | Bahari | 470841 | Batauwa | 40 | 32 | 80% | Work In Progress | Not Certified |
| 5 | Jaunpur | Ramnagar | Bahari | 470842 | Bahari | 162 | 130 | 80% | Work In Progress | Not Certified |