Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | UNIVERSAL MEP | 20066401 | DARIYAPUR GRAM PANCHAYAT WATER SUPPLY SCHEME | 465.36 | 280.67 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 27509.00 | 27355.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Waldirai | Dariyapur | 439333 | Dariyapur | 302 | 232 | 77 | Work In Progress | Not Certified |
| 2 | Sultanpur | Waldirai | Dariyapur | 439334 | Laharepur | 122 | 117 | 96 | Work In Progress | Not Certified |
| 3 | Sultanpur | Waldirai | Dariyapur | 439335 | Wallipur | 28 | 20 | 71 | Work In Progress | Not Certified |
| 4 | Sultanpur | Waldirai | Dariyapur | 439336 | Saflepur | 142 | 136 | 96 | Work In Progress | Not Certified |