Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Kannauj
AGENCY GVPR
SCHEME ID 20066445
SCHEME NAME NANDLALPUR & GHILOY KHAS GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST 240.75
EXPENDITURE 205.84
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 8702.00 Meter
Length Laid 8702.00 Meter

Scheme Assigned Villages

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Kannauj Chhibramau Ghiloee Khas 418797 Ghiloee Khas 217 217 100% Har Ghar Jal Not Certified
2 Kannauj Chhibramau Ghiloee Khas 418798 Sarai Bhim 48 48 100% Har Ghar Jal Not Certified
3 Kannauj Chhibramau Nandlal Pur 418812 Khanpur Kurmi 127 127 100% Har Ghar Jal Certified
4 Kannauj Chhibramau Nandlal Pur 418813 Nandlal Pur 134 134 100% Har Ghar Jal Certified