Scheme Details
DISTRICT
Kaushambi
AGENCY
GA INFRA - BABA (JV)
SCHEME ID
20066508
SCHEME NAME
Alai Urf Bakshipar water supply scheme
ESTIMATED COST
395.76
EXPENDITURE
253.06
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
1
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
19709.00
Meter
Length Laid
19409.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | Sarsawan | Alai Urf Bakshipar | 431114 | Alai Urf Bakshipar | 735 | 735 | 100% | Har Ghar Jal | Not Certified |