Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20066638 | RAM NAGAR 1 VILLAGE WATER SUPPLY SCHEME | 266.55 | 139.10 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 16 | Yes | 0 | NA | No | 13342.00 | 11030.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Ramnagar | Ram Nagar No. 1 | 470761 | Gaddopur | 72 | 68 | 94 | Work In Progress | Not Certified | 
| 2 | Jaunpur | Ramnagar | Ram Nagar No. 1 | 470762 | Ram Nagar | 174 | 143 | 82 | Work In Progress | Not Certified | 
| 3 | Jaunpur | Ramnagar | Ram Nagar No. 1 | 470763 | Bidhmiauwa | 82 | 62 | 76 | Work In Progress | Not Certified |