Scheme Details
DISTRICT Etawah
AGENCY OMIL-JWIL (JV)
SCHEME ID 20066701
SCHEME NAME ABHINAYPUR PATHAKPUR W/S SCHEME
ESTIMATED COST 234.75
EXPENDITURE 164.82
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 12148.00 Meter
Length Laid 11880.00 Meter

Scheme Assigned Villages

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Etawah Basrehar Abhinaypur Pathakpur 419725 Ivanepur Pathakpur 159 148 93% Work In Progress Not Certified
2 Etawah Basrehar Abhinaypur Pathakpur 419726 Kunaiya Ramnagar 169 149 88% Work In Progress Not Certified
3 Etawah Basrehar Abhinaypur Pathakpur 419727 Mungapur 120 116 97% Work In Progress Not Certified